The new Building Act No. 25/2025 Coll. takes effect on 1 April 2025

With effect from 1 April 2025, the new Building Act No. 25/2025 Coll. comes into force, bringing changes to the permitting of buildings. The details of this process, and the content and scope of the required documentation, will be regulated in implementing regulations (decrees). These are being prepared by the Office for Spatial Planning and Construction of the Slovak Republic, but their final form has not yet been published.

Key changes in the new Building Act

The new Act replaces the previous Act No. 201/2022 Coll. on construction, which formed part of the 2022 construction reform. One of the most significant changes is a simpler permitting process – instead of two separate proceedings (zoning and building permit proceedings), a single administrative proceeding on the Building Intention (stavebný zámer) is introduced.

This measure eliminates two-stage decision-making and duplicate opinions of the authorities concerned. After the decision on the Building Intention is issued, the Building Project is drawn up; it is not subject to further proceedings but is verified by the building authority. The new legislation also lays down clear and transparent time limits for individual steps.

Although these changes are expected to speed up the work of the building authorities, note that obtaining the opinions of the authorities concerned and resolving any conflicts moves to the stage before the proceedings begin. This responsibility passes to the builder or their authorised designer.

Digitalisation of the construction process

Building documentation will generally be prepared electronically and stored in the Office’s information system – the so-called Construction Portal. The portal, launched on 1 April 2025, will enable more efficient communication with the building authorities and remove the need to print extensive documents.

Under the transitional provisions of the Building Act, a person may also carry out any procedural act under the new Act in paper form until 31 March 2029, and a natural person may do so after that date.

Changes to a building before its completion

Until now, proceedings on a change to a building before its completion were often used to adjust the design brief during construction. The new Act no longer allows such a “correction”. If changes to the verified project are planned during construction, the builder may – at the proposal of the site manager, designer or building supervisor – convene an extraordinary control inspection of the building before they are made.

If these deviations are not of a fundamental nature, the designer marks them in the Building Project and the site manager records them in the site log. A more significant deviation from the verified Building Project requires new proceedings on the Building Intention.

Implementing regulations

The content of individual submissions, the scope of building documentation, the structural and technical requirements for buildings and the rules for barrier-free use will be regulated in detail by decrees of the Office for Spatial Planning and Construction. These decrees have not yet been issued.

The new Building Act from the perspective of the authorised legal entity (EIC)

Pursuant to Section 18(5) of Act No. 124/2006 Coll., in conjunction with Section 22 of the Building Act, the authorised legal entity EIC is a legal entity concerned in the proceedings on the Building Intention where the building includes technical equipment and is intended to perform the tasks of an employer, or of a natural person who is an entrepreneur but not an employer.

For the purposes of proceedings under the Building Act, the builder is obliged to submit the design documentation of a building with technical equipment, and any changes to it, to the authorised legal entity for assessment.

Under Section 9 of the Building Act, design documentation is divided into the Building Intention, the Building Project, the Building Project for notification and the execution project.

The Building Intention represents the basic construction solution of the proposed building, including the fire safety requirements for the proposed building and its operation, its siting, and its connection to transport infrastructure and utility networks, and it forms the basis for the proceedings on the Building Intention.

The Building Project represents the structural and technical solutions of the building and its technical, technological and energy systems, including fire safety requirements, the building’s fire protection devices and its connection to transport infrastructure and utility networks, in line with the Building Intention. The Building Project forms the basis for constructing the building and carrying out construction works.

EIC is obliged, at the request of the builder or their authorised designer, to issue a Binding Statement on the Building Intention, stating the specific legitimate requirements to be incorporated into the Building Project.

The builder or their authorised designer requests a Compliance Clause from EIC where EIC has reserved, in its Binding Statement on the Building Intention, the assessment of the Building Project and raised requirements for its completion.

The time limit for the statement of the authorised legal entity EIC is 30 days from receipt of the request; for complex buildings it may be up to 60 days. If the authorised legal entity does not issue the Compliance Clause within the set time limit, the requirements set out in the Binding Statement are deemed met and the Compliance Clause deemed granted.

Under Section 25 of the Building Act, a building, a change to a completed building, the removal of a building and construction modifications to a building or land may only be carried out under a Building Project verified in the proceedings on the Building Intention, or on the basis of a notification.

Transitional validity of Decrees No. 453/2000 Coll. and No. 532/2002 Coll.

Pursuant to Section 84(23) of the Building Act, Decree of the Ministry of the Environment of the Slovak Republic No. 453/2000 Coll., which regulates the implementation of selected provisions of the Building Act, and Decree No. 532/2002 Coll. of the same Ministry, laying down details of the general technical requirements for construction and for buildings used by persons with limited mobility and orientation, remain valid and effective until the new implementing regulations take effect, and no later than 31 March 2027.

The new Building Act does not change the requirements for the technical documentation (design documentation) of technical equipment under Section 5 of Decree No. 508/2009 Coll.

Pursuant to Section 5(3) of Decree No. 508/2009 Coll., classified technical equipment may be manufactured, assembled at the place of its future operation and reconstructed only according to design documentation for which the authorised legal entity EIC has issued an Expert Opinion pursuant to Section 14(1)(d) of the Act, assessing the design documentation (the “Expert Opinion on documentation”). For classified electrical equipment, the Expert Opinion on documentation is required only for technical equipment in group A.

Useful links

Act No. 25/2025 Coll. amending certain acts (the Building Act) (in Slovak)

Act No. 124/2006 Coll. on occupational health and safety and on amendments to certain acts (in Slovak)

Decree No. 508/2009 Coll. laying down details for ensuring occupational health and safety with technical equipment (in Slovak)