STN EN 50341-2-23:2026 Applies Without a Transition Period: What About Lines in Progress?
From 1 November 2026, a new edition of STN EN 50341-2-23 applies. The standard contains the national normative aspects for overhead electrical lines exceeding AC 1 kV in Slovakia. The new edition replaces the January 2017 standard in its entirety, and the original standard was withdrawn on the same date. Neither a period of parallel validity of the two editions nor a transition period has been set.
For investors, designers and future operators of lines, this raises a very practical question: what happens to projects prepared according to the 2017 edition and to lines that are currently under construction? The answer is not given in the national foreword but directly in clause 1.2 SK.1 of the new standard.
What changed on 1 November 2026?
The standard STN EN 50341-2-23:2026-11 was issued on 1 November 2026 and announced in the Bulletin of the Slovak Office of Standards, Metrology and Testing (ÚNMS SR) No. 10/2026. It adopts the European standard EN 50341-2-23:2026, approved by CENELEC on 13 May 2026, and continues to build on the general part EN 50341-1:2012. The previous STN EN 50341-2-23:2017-01 was withdrawn as of 1 November 2026.
This is an extensive revision. The section on external clearances has grown the most, and new clauses have been added on design working life, wind turbines, pipelines and insulators in polluted environments. The national foreword does not contain a list of the changes, so designers must identify them themselves by comparing the two editions.
Can a line in progress be completed according to the old standard?
Yes, but not automatically at every stage. In clause 1.2 SK.1, the standard distinguishes between the stages a line may be in:
| Status of the line | What STN EN 50341-2-23:2026 says (clause 1.2 SK.1) |
|---|---|
| Line under construction | It may be completed according to the standards valid at the time the line project was prepared. The use of certain provisions of the new standard must be agreed between the parties involved. |
| Modifications retaining the original supports (repair of supports, replacement of insulation and conductors, replacement of earth wires, addition of a second circuit) | This is not a new line unless the project specification states otherwise. The standards valid at the time of design and construction of the line apply. |
| Temporary line | It is a new line. The time and duration of the temporary operation are decisive for the design. |
| Crossings of new and existing lines | The conditions must be stated in the project specification. |
The standard therefore expressly allows a line to be completed according to the original standard only if it is already under construction, which in practice means that the construction has obtained a final building permit.
Which changes may affect a project in progress the most?
- Larger external clearances Del1: from 1.0 to 1.1 m at 110 kV, from 2.0 to 2.2 m at 220 kV and from 3.0 to 3.4 m at 400 kV. The change affects clearances to buildings, roads, railways and other lines.
- Height above roads for lines up to 45 kV: a new national table requires 6.0 m + Del1 for bare conductors, but at least 7.0 m. Previously, the values from Table 5.12 of the general part EN 50341-1 applied.
- Height above ground in open country: at least 6.0 m instead of 5.6 m.
- New distances of supports: from motorways and first-class roads, from wind turbines and from metal pipelines.
- Double insulator sets above 45 kV: now mandatory also over third-class roads, tramway, trolleybus and cable car lines, ski lifts, public parks and car parks.
- Security loads also for lines up to 45 kV: with certain exceptions, torsional and longitudinal loads are now also considered for high-voltage lines.
If a route was designed right at the limit of the original values, switching to the new standard may mean taller supports, a different arrangement of supports or a change in the type of insulator sets. For a project that already has permits and agreements with landowners in place, the decision on which edition of the standard to use is therefore also an economic one.
Is the new standard binding at all?
Under Section 4(1) of Act No. 124/2006 Coll. on occupational health and safety, designers must prepare designs of technical equipment so that they meet the requirements of legal regulations and other regulations for ensuring occupational health and safety. Under Section 39(1) of the Labour Code, these other regulations also include technical standards. In practice, compliance with the valid Slovak technical standard is therefore the way to demonstrate the safety of the designed technical equipment.
The valid standard is the benchmark for the current state of the art. The investor, the future operator of the line and an independent inspection body all assess the project against it. An authorised legal entity therefore bases its assessment of the documentation on the valid edition of the standard, which from 1 November 2026 is STN EN 50341-2-23:2026.
A change of standard is not an administrative formality. Larger external clearances and stricter load requirements increase the safety margin of a line that will be in operation for decades. For lines above 45 kV, the new edition also sets, for the first time, a design working life of 80 years for supports and foundations.
Practical recommendations
- Overview of contracts in progress: find out which lines are under construction and which are at the design stage.
- Check of critical points: crossings of roads, railways and other lines and the proximity of buildings, wind turbines and pipelines should be checked against the new values.
- Modifications of existing lines: when replacing conductors or adding a second circuit, state explicitly in the project specification whether this is a new line.
- Temporary lines: design them according to the new edition, as the standard considers them new lines.
Conclusion
The new STN EN 50341-2-23:2026 took effect overnight. A line that is already under construction may be completed according to the original standard. The decision on which edition a line is designed to should be deliberate and demonstrable, not a silent continuation of “business as usual”. Responsibility for a safe design lies with the investor and the designer, not with the standard itself.
As an independent inspection body, EIC assesses the design documentation of buildings, including electrical lines, and can help you check how the changes to the standard affect a specific project. More information is available on the page Assessment of the design documentation of technical equipment.
Interesting links
Earthing of Electrical Equipment Above 1 kV AC
Who is an authorised legal entity (OPO) and when does your company need one?
Assessment of the design documentation of buildings
STN EN 50341-2-23:2026-11, normy.normoff.gov.sk (in Slovak)
Act No. 124/2006 Coll. on occupational health and safety (in Slovak)